Demolition of a 30m high, 40m x 110m storage warehouse containing high level racking throughout and two storey office blocks. Processing of all site-won hardcore to form 6F2 and type 1.

Our excellent high level of health & safety and professionalism reinforced the relationship and respect that Volker Fitzpatrick have with Demex.

Howard Smith Distribution

Contract Value

N/A

Client

Volker Fitzpatrick

Job Duration

20 Weeks

Completion Date

October 2018

2018

The works provided 3000 tonnes of scrap metal which was returned to our Parent group for further processing before feed back into the steel industry.